Galesi TBT - 2016

In 2016, brownfield cleanup of the Alco site was complete. The two year process consisted of importing hundreds of thousands of cubic yards of clean fill, to spread out and act as a clean cover to prep the site for development. The old foundations were pulled from the ground, crushed and reused on the site for parking lots and roads. #GGTBT